Home  |  New Laundry Project
 Assigned lease land  |  Pouring concrete of the loading dock  |  Progress till 23 of May 2007.  |  Finished steelbuilding May 25, 2007.  |  Progress of the project till 31 May 2007  |  Preparing for land cleaning  |  Cleaning the land  |  Cleaned land  |  Marking foundation new building  |  Ground breaking and escavation.  |  Foundation lineup.  |  Erecting the office walls.  |  Floor of new building  |  Building the office and cafeteria.  |  Filling of floor foundation  |  Finishing waterdrain and watertanks.  |  Pouring floor with concrete  |  Preparing floor to pour concrete  |  Preparing deck of water reservoir  |  Erecting steel frame  |  Paneling the roof  |  Progress 2-14 May. 

These photos are of the asigned lease land located in the industrial area at Barcadera.

August 9, 2006.