Assigned lease land
|
Pouring concrete of the loading dock
|
Progress till 23 of May 2007.
|
Finished steelbuilding May 25, 2007.
|
Progress of the project till 31 May 2007
|
Preparing for land cleaning
|
Cleaning the land
|
Cleaned land
|
Marking foundation new building
|
Ground breaking and escavation.
|
Foundation lineup.
|
Erecting the office walls.
|
Floor of new building
|
Building the office and cafeteria.
|
Filling of floor foundation
|
Finishing waterdrain and watertanks.
|
Pouring floor with concrete
|
Preparing floor to pour concrete
|
Preparing deck of water reservoir
|
Erecting steel frame
|
Paneling the roof
|
Progress 2-14 May.
Contractor is preparing the deck of the water reservoir February 7 thru 10, 2007.
|
|